Expansion Update – Still on Schedule – Pavement Down

The expansion is still on schedule to be completed mid-September.  In this picture we’re getting the first 2 inches of pavement being put down last Friday.

Expansion Update – Continuing On Schedule

Our 62,000 Sq. Ft. expansion continues on schedule.  Today the last of the concrete is being poured inside for the flooring.  Work also continues on the connection between the new building and the existing building.

Update from Clow Stamping

Significant growth during the last three years peaked in early 2012 and presented CSC with some challenges in meeting the on-time delivery requirements of our customers. To avoid compromising deliveries, several solutions have been implemented. In addition to the ongoing 72,000 sq ft expansion, 2.9 million in equipment purchases were made. To alleviate a labor […]

Expansion Update – Phase 2 On Schedule

The Merrifield area has received considerable rainfall this summer. Over 7.5 inches in June and over 4 inches in July so far. That much rain has been hampering construction efforts. Nevertheless, the contractor, says the 62,000 Sq. FT. project is on schedule to be completed in September. The exterior concrete walls are being delivered and […]

Microsoft Dynamics NAV ERP Software Implementation Progress Report

While the overall progress of the NAV implementation has been much slower than originally estimated due to the volume and complexity of the data we need to transfer between systems, some important functionality has been successfully brought on line. In January we went live with Payroll. Processing Payroll in house will save Clow Stamping Company […]

Ready to Connect?

We look forward to quoting your future requirements and thank you for allowing Clow Stamping Company to serve your needs.